Chinese New Year, APEC and the other dates that delay a custom product run

By Keenan Johns, Founder of Protocol Ritual LLC · · 2 min read

Chinese New Year 2027, February 6

A custom product run is built on a factory calendar, and that calendar has a few dates that move everything around them. Miss one, and a run that should have taken six weeks takes twelve. These are the dates we plan around, and what they mean for a clinic ordering now.

Chinese New Year: the big one

Chinese New Year 2027 falls on Saturday, February 6. It is the longest shutdown of the manufacturing year.

The holiday itself is about a week. The effect on production is much longer:

  • Before: factories start slowing down several weeks ahead. Workers travel home early, lines wind down, and freight space fills up as everyone tries to ship at once.
  • During: most factories stop.
  • After: not every worker comes back, and new staff have to be trained. Many factories run below full capacity into March.

In practice, a clinic should treat mid-January through early March as a period where new production barely moves.

What that means for an order: a custom run usually needs proofs, a sample, production and inspection before it ships. To ship before the slowdown, production generally needs to finish by early December. An order placed after that is likely to be built after the holiday, with delivery in March or later.

APEC 2026: Shenzhen, November 18–19

The APEC Economic Leaders' Meeting is in Shenzhen on November 18 and 19, 2026, with the CEO Summit on November 17 and 18. Shenzhen and the surrounding Pearl River Delta are home to many of the factories that make electronics, cases and packaging.

Host cities tighten security and traffic around events like this, and Shenzhen began new traffic rules for scooters and delivery riders months ahead. For a supplier in the area, that week can mean slower pickups, slower courier runs and delayed deliveries. Not every factory is affected, and the effect should be short, but it lands right before the pre–New Year rush. Ask your supplier whether they are in the area and what they expect.

The other dates on the calendar

  • Golden Week, October 1–7. China's National Day holiday. Most factories close for the week, and the weeks around it run slower.
  • Labor Day, early May. A shorter holiday of several days, with a slowdown around it.
  • US peak shipping, November to December. Carriers are at their busiest and add peak-season surcharges. Air freight space is tight before Christmas, the same weeks factories are rushing to ship before Chinese New Year.

How we plan around them

  • We work backwards from the holiday. For a run that has to land before Chinese New Year, the order, the proofs and the sample have to be done early enough that production finishes in time.
  • We tell a clinic the real date. If an order can't land before the holiday, we say so when it is placed, not in February.
  • We ask each factory for its own schedule. Closure and reopening dates vary by factory and region. The dates above are a guide; the factory's calendar is the answer.

How a custom product run works walks through each stage of a run, and Protocol Ritual for brands covers how a run reaches each member.

Get a quote and we'll tell you what lands before February 6.

Questions

When is Chinese New Year 2027?

Saturday, February 6, 2027. Factories start slowing down several weeks before it, and many run with reduced staff into March.

When should a clinic order to have product before Chinese New Year?

For a custom run, production generally needs to finish by early December so it can ship before the slowdown. Orders placed after that are likely to be built after the holiday, with delivery in March or later.

Does APEC 2026 affect shipping?

APEC leaders meet in Shenzhen on November 18 and 19, 2026. Expect tighter security and traffic controls in and around the city that week, which can slow pickups and deliveries for suppliers based there. Ask your supplier how it affects their schedule.